My Profile

Blue Light Report - July / August 2019

Dear Brothers and Sisters,

Like many of you, I am also disappointed in the many projects that have been stalled or delayed. All the more reason we must continue to be vigilant in our efforts to advocate. Sadly, only about 50% of our members are actively engaged on our Action Network.

Social News

My Action Profile
Blue Light Report Central - July / August 2019

Pipeline construction activities have seen a slow first quarter for 2019 with many projects being pushed back because of permitting issues, but it seems the work may be picking up a bit. Since my last report, I have held 24 pre-jobs that included mostly integrity maintenance projects, and the Price Gregory work in the Upper Peninsula of Michigan for SEMCO Energy.

Currently, we are watching the Buckeye XPress progress, which is anticipated to start the first quarter of 2020.  This Southern Ohio project received the initial FERC approval and is now in the appeal stage. Please follow along on the Action Network. Tell FERC you support both the Buckeye XPress Project and Enbridge’s Line 5 in Michigan by signing the petitions at www.action.local798.org

Always keep in mind that how we conduct ourselves on and off the ROW is a reflection of not only ourselves but our Local Union.  Being prepared, no absenteeism, using the chain of command, following the agreement, and maintaining our working conditions are all part of a fair day’s work for a fair day’s pay.  Unfortunately, we still have members who think they can cross over to the non-union side of the fence.  I have been out investigating and identifying some who are working on non-union pipeline projects.  It seems the Interstate 70 corridor in Eastern Ohio is a hotspot.  If you are one of these members who think you can get away with working non-union, don’t be surprised if you receive official charges filed against you for these offenses.  I appreciate all the assistance from my Brothers and Sisters who have helped confirm these violations. 

I have several trips scheduled for June and July job visits.  Until then, keep up the good work and make the right name for yourself.  You decide what will be said of your reputation.  As always if I can be of assistance, please don’t hesitate to call me.    

Pre-jobs:

Big Inch Fabricators and Construction, Inc.:

- Indianapolis, IN.  3 tee replacements 30” and 24” for Panhandle Eastern Pipeline.  Superintendent: Chris Elliott. Welder Foreman: Layne Richard.  Working 6-10s.  Job complete.

- Concord, MI.  1-12” anomaly and 4” meter station for Panhandle Eastern Pipeline.  Superintendent: Chris Elliott.  Welder Foreman: Layne Richard.  Working 6-10s.  Approx. completion 7-14-19.

Foltz Welding:

- Hamilton County, IN.  Isolate and hydrotest 10.6 miles of 24” pipeline for ETC Panhandle Eastern Pipeline.  Superintendent: Scott Schoonover.  Welder Foreman: Levi Tolka.  Working 6-10s.  Approx. completion 7-3-19.

Henkels & McCoy:

- Toledo, OH.  Maintenance services, fabrication, anomaly investigation and miscellaneous repairs in various locations and pipe sizes in OH, MI, and PA for Buckeye Partners.  Superintendent: Jeff Karsten.  Welder Foreman: Gary Mullin.  Working 5-10s.  Approx. completion 12-31-19.

- Lucas, OH.  OH class change project, hydrotest approximately 1.8 miles of 20” for TransCanada Corp.  Superintendent: David Csepegi.  Welder Foreman: Timothy Hathaway.  Working 6-10s.  Approx. completion 7-3-19.

InfraSource Construction:

- Harrison, OH.  Facility modifications with multiple diameters in Hamilton County, OH for Duke Energy.  Superintendent: Calvin Fuller.  Welder Foreman: Brian Graham.  Working 6-10s.  Approx. completion 8-15-19.

Latex Construction:

- Elyria, OH.  Drain tile repair and replacement of approximately 14 miles of ROW for Nexus Gas.  Superintendent: Cotton Jordan.  Working 6-10s.  Approx. completion 7-31-19.

LMC Industrial Contractors:

- Hanoverton, OH.  30” and 20” hot tap and bridle piping for Kinder Morgan.  Superintendent: Randy Vermeulen.  Welder Foreman: Mike Trevett.  Working 5-10s.  Approx. completion 6-21-19.

Meade:

- Xenia, OH.  Install small station with approximately 150’ of 4” and 50’ of 6” and 7 miles of 20” hydro test for Vectren.  Superintendent: John Karlson.  Welder Foreman: Troy Allen.  Working 6-10s.  Approx. completion 8-15-19.

- Warsaw, IN.  2,235’ of 20” and replacement of 8 ditch crossings, replacement of 15 elbows/bends, upgrade 4 regulator stations for NIPSCO.  Superintendent: John Karlson.  Welder Foreman: Jason Spurgeon.  Working 6-10s.  Approx. completion 9-15-19.

Michels Pipeline:

- Ispeming, MI.  Receiver removal project for Northern Natural.  Superintendent: Scott Battisti.  Welder Foreman: Johnny Gardner.  Working 6-10s.  Approx. completion 6-12-19.

Mid-Western Contractors:

- Huron, OH.  2”-12” station work, regulation runs, maintenance of existing facilities, and tie-ins to existing pipelines for NiSource.  Superintendent: Martin Ankenbruck.  Welder Foreman: Michael Kortkamp.  Working 6-10s.  Approx. completion 8-5-19.

Minnesota Limited:

- Detroit, MI.  Detroit River crossing HDD 16” through 24” casing welds in Wayne County, MI for Kinder Morgan.  Superintendent: Duane Carlson.  Welder Foreman: Eric Haskins.  Working 6-10s.  Job complete.

- Wellsville, OH.  1,650’ of 20” pipeline, launcher/receiver, M & R station for Burns and McDonnell.  Superintendent: Aaron Shrontz.  Welder Foreman: Matt Delik.  Working 6-10s.  Approx. completion 10-26-19.

- West Lafayette, IN.  Integrity repair on 16” pipeline, remove and replace 8 filter/regulator sets, install one stopple and 2 gage risers for Vectren.  Superintendent: Tommy Alexander.  Welder Foreman: Robert Turner.  Working 6-10s.  Approx. completion 6-20-19.

NPL Construction Company:

- Decatur, IN.  12” and 16” station, replace heater and odorant tank for NIPSCO.  Superintendent: Nick Sturwold.  Welder Foreman: Mark Antczak.  Working 5-10s.  Approx. completion 6-13-19.

PJ Steel:

- Reed City, MI.  16”/12”/14” install pig trap and future odorizer piping for DTE Gas.  Superintendent: George Lewis.  Welder Foreman: Jason Carlson.  Working 5-10s.  Approx. completion 6-24-19.

Price Gregory International:

- Marquette, MI.  36 miles of 20” and 6.8 miles of 10” with fabrication for SEMCO Energy.  Superintendent: Todd Burleson.  Welder Foreman: Jeremy Padgett.  Working 6-10s.  Approx. completion 10-1-19.

Union Pipeline Incorporated:

- Cadiz, OH.  9,012’ of 12” new lay in Jefferson County, OH for Mark West.  Superintendent: Perry Rogers.  Welder Foreman: Eric Raymond.  Working 5-10s.  Approx. completion 7-1-19.

United Piping Incorporated:

- Mt. Pleasant, MI.  Two locations- cut-out and replace 120’ of 16” in Oakland County, MI and 120’ of cut-out and tie-in to existing 12”, run 100’ of 2” in Bay County, MI for Consumers Energy.  Superintendent: Jim Mitchell.  Welder Foreman: Torey Maki.  Working 6-10s.  Job complete. 

- Dillonvale, OH.  Install pipe support beams at the TEAL compressor station for Enbridge.  Superintendent: Bob Humphrey.  Welder Foreman: George Houston.  Working 6-10s.  Approx. completion 9-30-19.

VEC:

- Hubbard, OH.  1”- 4” fabrication of a 2” regulator system for TransCanada.  Superintendent: Sean Wilster.  Welder Foreman: Jeffery B. Mooney.  Working 5-10s.  Job complete.

MORE 798 STORIES

  • Blue Light Report - July / August 2019
    Dear Brothers and Sisters, Like many of you, I am also disappointed in the many projects that have been stalled or delayed. All the more reason we must continue to be vigilant in our efforts to advocate. Sadly, only about 50% of our members are actively engaged on our Action Network.
  • Blue Light Report 2 - July / August 2019
    Brothers and Sisters, I hope this report finds each of you healthy and in good spirits. This year has obviously started out much slower than the last two. Through the month of May, we are well behind 2017 and 2018 man-hours, but we are still ahead of 2015 and 2016, which ended up being 6.8 million and 7.5 million man-hour years.
  • Blue Light Report Dispatch - July / August 2019
    The pipeline hours are slower than in 2017 and 2018, but we are still ahead of 2015 and 2016, so work is not quite as slow as it may seem. We are not having a record year as we have had previously (that goal is unreasonable), but work is picking up.  We have already needed to PPC-11 a nonbook to an Intermediate job in the Dakotas.
  • Blue Light Report Benefits Update - July / August 2019
    401(k) Distributions We are currently experiencing an unusually high volume of 401(k) calls and distribution applications. Please know that messages received by the Fund office will be returned and we are working to process the distribution applications in a timely manner.